Content Validity Index (CVI): Formula, I-CVI, S-CVI and Worked Example

In short The content validity index (CVI) measures how relevant experts judge the items of an instrument to be. Experts rate each item on a 4-point relevance scale; the item-level CVI (I-CVI) is the proportion of experts rating the item 3 or 4. The scale-level CVI can be the average of all I-CVIs (S-CVI/Ave) or the proportion of items rated 3 or 4 by all experts (S-CVI/UA). Commonly cited standards are I-CVI of 1.00 with three to five experts, at least 0.78 with six or more experts, and S-CVI/Ave of at least 0.90.

Key takeaways

  • Experts rate each item: 1 = not relevant, 2 = somewhat relevant, 3 = quite relevant, 4 = highly relevant.
  • I-CVI = experts rating 3 or 4 ÷ total experts.
  • S-CVI/Ave = average of all I-CVIs; S-CVI/UA = items rated 3–4 by every expert ÷ total items.
  • Commonly cited targets: I-CVI 1.00 (3–5 experts), ≥ 0.78 (6+ experts); S-CVI/Ave ≥ 0.90.
  • Revise or remove low-scoring items, then report the final values in your methodology.
On this page
  1. What is content validity?
  2. Step 1 — Choose your experts
  3. Step 2 — Rate each item on a 4-point scale
  4. Step 3 — Compute I-CVI for each item
  5. Worked example (5 experts, 6 items)
  6. Step 4 — Compute the scale-level CVI
  7. Step 5 — Interpret and revise
  8. Optional: modified kappa
  9. How to report CVI in your methodology

What is content validity?

Content validity is the degree to which an instrument's items represent everything they are supposed to measure. The content validity index (CVI) turns expert judgement into numbers so that you can report it objectively. The approach is widely attributed to Lynn (1986), with later guidance on scale-level CVI by Polit and Beck (2006).

Step 1 — Choose your experts

Use three to ten experts with relevant knowledge — for example subject teachers, researchers in the field and a measurement or research-methods specialist. Give each expert the research objectives, the definitions of each variable and a rating sheet.

Step 2 — Rate each item on a 4-point scale

RatingMeaning
1Not relevant
2Somewhat relevant
3Quite relevant
4Highly relevant

Ratings of 3 and 4 count as relevant; 1 and 2 count as not relevant. A 4-point scale avoids a neutral middle option.

Step 3 — Compute I-CVI for each item

I-CVI = number of experts rating the item 3 or 4 ÷ total number of experts

Worked example (5 experts, 6 items)

ItemE1E2E3E4E5Experts rating 3–4I-CVIAll agree?
14434451.00Yes
23443451.00Yes
34243440.80No
44444351.00Yes
52324330.60No
64344451.00Yes

Step 4 — Compute the scale-level CVI

  • S-CVI/Ave = average of the I-CVIs = (1.00 + 1.00 + 0.80 + 1.00 + 0.60 + 1.00) ÷ 6 = 0.90
  • S-CVI/UA (universal agreement) = items rated 3–4 by all experts ÷ total items = 4 ÷ 6 = 0.67

Step 5 — Interpret and revise

How to calculate the content validity indexFive experts rate six items on a four-point relevance scale. I-CVI is the number of experts rating 3 or 4 divided by the number of experts. Items 1, 2, 4 and 6 score 1.00, item 3 scores 0.80 and item 5 scores 0.60. S-CVI/Ave is 0.90 and S-CVI/UA is 0.67. With three to five experts each item should reach 1.00; with six or more, at least 0.78; S-CVI/Ave should be at least 0.90.Content validity index (CVI) — worked example5 experts rate each item: 1 not relevant · 2 somewhat · 3 quite · 4 highly relevantI-CVI = experts rating 3 or 4 ÷ total expertsItemE1E2E3E4E5Rated 3–4I-CVIResult14434451.00Keep23443451.00Keep34243440.80Revise44444351.00Keep52324330.60Revise or drop64344451.00KeepS-CVI/Ave = average of I-CVIs = 0.90S-CVI/UA = 4 of 6 items all-agree = 0.67Targets: I-CVI 1.00 (3–5 experts),≥ 0.78 (6+ experts); S-CVI/Ave ≥ 0.90
Figure 1. Item- and scale-level CVI for the worked example with five experts.

Commonly cited standards (Lynn, 1986; Polit & Beck, 2006):

IndexAcceptable value
I-CVI with 3–5 experts1.00
I-CVI with 6–10 expertsat least 0.78
S-CVI/Aveat least 0.90
S-CVI/UAat least 0.80

In the example, items 3 and 5 fall short with five experts. Revise their wording using the experts' comments — or remove them — and, ideally, ask the experts to rate the revised items again. S-CVI/UA is strict and falls quickly as the number of experts rises, so many researchers report S-CVI/Ave as the main scale index.

Optional: modified kappa

Because experts can agree by chance, Polit, Beck and Owen (2007) suggested adjusting each I-CVI with a modified kappa (k\). If your supervisor asks for it, compute the probability of chance agreement for each item and report k\ beside the I-CVI.

How to report CVI in your methodology

The instrument was validated by five experts — two senior high school teachers, two education researchers and one research-methods specialist — who rated each item on a four-point relevance scale. Item-level CVIs ranged from 0.60 to 1.00. Two items with I-CVI below 1.00 were revised based on expert comments. After revision, all items obtained an I-CVI of 1.00, and the S-CVI/Ave was 1.00.

Content validity is only one step. Also run a pilot test and check reliability (for example Cronbach's alpha) — see research instrument: types and validation.

Frequently asked questions

How many experts do I need for CVI?

At least three; many studies use five to ten. With fewer than six experts, each item should normally be rated relevant by all of them (I-CVI = 1.00).

Can I use a 5-point scale for CVI?

The standard method uses a 4-point relevance scale so that ratings divide cleanly into relevant (3–4) and not relevant (1–2). If you use another scale, explain how you dichotomised it.

What is the difference between S-CVI/Ave and S-CVI/UA?

S-CVI/Ave averages the item-level indices; S-CVI/UA counts only items that every expert rated relevant. S-CVI/UA is stricter and becomes harder to achieve as you add experts.

Is CVI the same as reliability?

No. CVI is evidence of content validity — whether items measure the intended content. Reliability is about consistency of scores and is usually tested with a pilot study and Cronbach's alpha.

Do I need CVI if I adopt a validated questionnaire?

Not always. If you adopt an instrument unchanged and it was validated in a similar population, cite its validation. If you adapt wording or context, re-check content validity.

Who can be an expert validator?

People with relevant subject or measurement expertise — for example teachers or practitioners in the field, researchers who study the topic, and a research-methods specialist.

What should I do with items that fail the CVI?

Revise the wording using the experts' comments, or remove the item. Ideally, ask the experts to rate revised items again before the pilot test.

Where do I put the CVI results in my thesis?

Report the CVI values in the research instrument section of the methodology chapter and attach the experts' rating sheets in the appendix.

R
RSIS Editorial TeamEditorial & Publishing Desk, RSIS International

The RSIS editorial desk manages peer review and production for four open-access journals (IJRISS, IJRSI, IJRIAS, IJLTEMAS) and writes these guides from day-to-day editorial experience.

Cite this guide: RSIS Editorial Team (2026). Content Validity Index (CVI): Formula, I-CVI, S-CVI and Worked Example. Gyaanarth. https://gyaanarth.com/research-guides/content-validity-index-cvi

More in Research Methods & Data Analysis